Information required for Municipal Engineering Construction:
1、 Preparation stage documents
1. Project documents, construction drawing examination certificate, planning permit, construction permit and Quality Supervision Certificate
2. Geological Survey Report
2、 Construction process documents
construction management
Unit business license and qualification (laboratory, measuring instrument,), work safety license, project department application and relevant personnel post certificate
construction technique
1. Construction organization design and approval, (general, safety, winter, rainy season, temporary power, road, sewage, deep trench excavation and protection construction, rainwater, bridge, bored pile, bridge engineering hoisting scheme, pier column, capping beam construction scheme, prestressed tension scheme, pile foundation, etc.)
2. Appointment, assignment, drawing review summary, commencement report and extension report
3. Technical disclosure record, work contact list and design change
Construction record
1. Survey (pile delivery record, survey review record; construction survey and setting out record)
2. Rebound deflection record, bored pile drilling, hole forming record, bored pile underwater concrete pouring record, prestressed concrete tensioning record, duct grouting record, concrete pouring record, temperature measurement record, settlement observation record, etc
3. Construction log
3、 Construction test documents
4、 Construction quality inspection documents
5、 Construction acceptance
Completion report, construction description and completion elevation
6、 As built drawings
Supervision notice and reply
Application for inspection and first article inspection of concealed works in quality inspection station
Party A's documents
Weekly plan, monthly plan
Operation instruction
Standards and specifications